Q:

What information is required to process a change to a baseline?

belongs to collection: SOFTWARE MANAGEMENT MCQ

0

What information is required to process a change to a baseline?


  1. Reasons for making the changes
  2. A description of the proposed changes
  3. List of other items affected by the changes
  4. All of the mentioned

All Answers

need an explanation for this answer? contact us directly to get an explanation for this answer

(d).All of the mentioned

need an explanation for this answer? contact us directly to get an explanation for this answer

total answers (1)