Which of the following is not a project factor that should be considered when planning the structure of software engineering teams?

0

Which of the following is not a project factor that should be considered when planning the structure of software engineering teams?


  1. The difficulty of the problem to be solved
  2. High frustration caused by personal, business, or technological factors that causes friction among team members
  3. The degree of sociability required for the project
  4. The rigidity of the delivery date

All Answers

need an explanation for this answer? contact us directly to get an explanation for this answer

(c).The degree of sociability required for the project