Q:

Which two models doesn’t allow defining requirements early in the cycle?

0

Which two models doesn’t allow defining requirements early in the cycle?


  1. Waterfall & RAD
  2. Prototyping & Spiral
  3. Prototyping & RAD
  4. Waterfall & Spiral

All Answers

need an explanation for this answer? contact us directly to get an explanation for this answer

 (b).Prototyping & Spiral